In order to elaborate urbanism documentations: Zonal Urban Plan (PUZ), Detailed Urban Plan (PUD), General Urban Plan (PUG) or drafting the project Authorization for construction execution it is necessary to draft a technical approval endorsed by OCPI.

Required documents
- Cadastral documentation – copy
- Land book extract for informationExtras de carte funciara pentru informare
- Property documents – copy
- Urbanism certificate – legalized copy
- Extract of the plot plan issued by the City Hall (only for the CAP)
- Copy of the owner’s CI or CUI in the case of legal entities
- Notice of commencement of works.

Execution term
2-3 working days

Term of approval
- Normal regime: 15 working days
- Emergency regime: 5 working days

OCPI taxes
- Normal regime: between 200 and 1500 lei, depending on the area
- Emergency regime: between 1000 and 6500 lei depending on the area

Documents handed over
- Minutes of receipt of the technical approval
- Location and delimitation plan (2 copies)